PROJECT OVERVIEW:
 
TP Power Services were contracted to complete the installation and commissioning of 2 off 18MVA, 132/26.5kV Single-Phase Transformers at Scottish Power Bathgate substation, Glasgow. With both main 70MVA Unit Transformers live throughout the project, additional safety procedures were implemented with a strong focus on planning, co-ordination with other contractors, assessment of lifting procedures, as well as planning the movement of large plant under the 132kV live overhead lines. TP Power Services completed the installation and commissioning for handover ahead of schedule for Scottish Power
 
SCOPE OF WORKS:

 
   Receipt & Quality Inspection of auxiliary items
   Assiting with the final positioning of both transformers onto their respective plinths
   Installation of auxiliary components, control and protection instruments and local control panels
   Wiring local control panels and testing to local protection circuits
   Vacuum, oil processing and circulation of mineral insulating oil to achieve 5 ppm and 75kV
   Full Pre-Commissioning tests after installation - including Sweep Frequency Response Analysis (SFRA) & Tan-Delta
   Final Commissioning work
 

TP Power Services completed a variety of modification and variation works to the transformer to meet Scottish Power QA requirements, requiring involvement within the design and quality process to identify and implement corrective actions.

 
 
PERFORMANCE REVIEW:

"I was pleased with the professional approach TP Power Services took towards the work, their technical competency and willingness to assist in progressing the work,  i look forward to working with you in the future"

 

John Easton - Project Manager, Iberdrola Engineering & Construction

KPI score awarded:          91%

 
FURTHER ACTION:

 
TP Power Services have completed all the works associated with this project and continue to work with Scottish Power & Scottish Power Renewables on other projects.
 

 

 

 

 

Posted by B.A on 6 January 2011

 

Read more latest news stories...

 

About Us:

Established in 2000 by a group of electrical engineers specialising in transformers and switchgear; we have grown to offer fully integrated substation services.....

Read More...

Clients:

TPPS have built relationships with our key clients and developed our systems to ensure that we continue to meet their performance expectations.....

Read More...

Corporate Responsibility:

The company operates under an IMS based on the International Standards of Quality (ISO9001), Environmental (ISO14001) and Health & Safety (OHSAS18001).....

Read More...

TP Power Services Ltd, Head Office, Rempstone Road, Wymeswold, Loughborough, Leics, LE12 6UE, England

Telephone:
Fax:
Web Site:
Email:
Site Design: